Manufacturing Planning and Execution

Revised 04/04/1999

The first step in general manufacturing planning is to create independent demand requirements for each product. For some products, MSI forecasters and master planners create a complete Sales and Operations Plan (SOP). For other products, the forecasters create the independent requirements direcdy. In these exercises, the MSI planners have already created the Sales and Operations Plan (SOP).

After creating the independent requirements, MSI's master planners create a Master Production Schedule (MPS) for each finished producL The master planners use this production schedule to confirm the highlevel production activities hefore the detalled requirements are calculated.

Next, MSI runs Material Requirements Planning (MRP) to determine the dependent requirements and plan the supply of all components listed in each finished product's bill of material. This process satisfies requirements for all components, including both manufactured and purchased materials.

Finally, the MSI production controller releases production orders to the shop floor, issues the appropriate quantity of component material, reports production activity (such as labor time), completes the production order, and receives the goods into inventory.

In this exercise you will create a Sales and Operations Plan for a motorcycle. This plan will create production orders for the finished product. The MRP for the finished product will also create a production order for a subassembly, the powertrain. You will carry out the manufacture of the subassembly only in this example.


DISPLAY THE SOP PLAN

MENU PATH

Logistics>Production>SOP>Planning>For Material>Change

Field Name Input data
Material 1300-1500-xxx
Plant 3000
Version Active

Fill in the Production Plan for the Next Four months

Month Quantity
month1 50
month2 100
month3 75
month4 25

Make sure priduction levels are blank for all four months

Select enter icon to continue

Select the save icon

DISPLAY THE STOCK/REQUIREMENTS LIST TO VIEW ANY PLANNED REQUIREMENTS

MENU PATH

Logistics>Production>Master Planning>Demand management>Environment>Stock/reqmts list

Field Name Input Data
Material 1300-1500-xxx
Plant 3000

Select Enter icon

Record the independent requirements for months 1-4

RESULTS

month1____________

month2____________

month3____________

month4____________

CREATING A PRODUCTION PLAN

Change the sales and operations plan and create a production plan for the material specified.

MENU PATH

Logistics>Production>SOP>Planning>For material>Change

Field Name Input Data
Material 1300-1500-xxx
Plant 300
Version Active
Target Stock Level 25 for each month

Use the following menu path to carry out the production plan using these target stock levels.

MENU PATH

Edit>Create production plan>Target stock level

Record the new production plan for the next four months

Month1 _____________

Month 2_______________

Month 3_______________

Month 4

Select the save icon to change the production plan

TRANSFER THE PLANNING VALUES TO DEMAND MANAGEMENT

MENU PATH

Logistics>Production>SOP>Disaggregation>Trsf.mat to dm mngt

Field Name Input Data
Material 1300-1500-xxx
Plant 3000
Version A00
Production plan for material or PG members select
fro today's date
Invisible transfer deselected
Active selected

Select the Transfer now button

Note: you might receive a message "Requirement was already available and was changed" This will occur if there is an existing demand plan created via SOP. If you receive this message your transfer is complete and you should only record the requirements type.

Select the enter icon

Record the Requirements type and the planned quantity

RQType _______________

Planned quantity _____________

Select the Save icon


Display the stock/requirements list to view the changed planned independent requirements.

MENU PATH

Logistics>Production>Master planning>Demand management>Environment>Stock/reqmts list

Enter the following data

Field Name Input Data
Material 1300-1500-xxx
Plant 3000

Select enter icon

Record the independent requirments for months 1-4

______________

______________

______________

______________


Run single-item, single level MPS for the material specified.

MENU PATH

Logistics>Production>Master planning>MPS>MPS>Sng-item,sng-level

Field Name Input Data
Material 1300-1500-xxx
Plant 3000
Processing key NETCH
Create pur. req 3
Deliv. Schedule 1
Create MRP list 1
Planning mode 1
Scheduling 1
Planning date Today's date
Display result select

Select enter icon

Note the systems displays the warning message "Please check input parameters"

Select the enter icon again

RESULTS

Are there any new MRP elements?

_____________________________________________________________

Select the SAVE icon.

To see the Bill of Materials for the Finished Product

MENU PATH

Logistics>Production>Master Data>Bill of Materials>Bill of Material>Material BOM>Display

Field Name Input Data
Material 1300-1500-xxx
Plant 3000
BOM Usage 1

Select enter icon to continue

How many assemblies are required for the finished product?

________________________


Display the MRP list for the material to confirm the results of the MPS run.

The MRP list should now reflect the independent requirements values entered in the sales and operations plan and the planned orders for the top level material generated in the MPS run.

MENU PATH

Logistics>Production>Master planning>MPS>Evaluations>MRP list- material

Field name Input data Material
Material 1300-1500-XX
Plant 3000

Select Enter icon to continue

Are there any independent requirements from the sales and operations plan?

__________________________

Were any planned orders generated during MPS

___________________________

Do not back totally our of this transaction until you read the next activity.


Display the stock requirements list for a direct component of material 1300-1500-xxx The direct componenets of this top-level material reflect only dependent requirements, and no planned orders.

Access the stock requirements list, by clicking the Back icon until you reach the Master Production Scheduling screen

Select the following path:

MENU PATH

Evaluations>Stock/requirmts list

Field Name Input Data
Material 2300-101-xxx
Plant 3000

Select the enter icon

Are there any dependent requirements generated during MPS?

______________________

Are there any planned orders?

______________________



Run single-item, multi-level MRP for the material specified. Determine the materials that were included in the planning run.

MENU PATH

Logistics>Production>MRP>MRP>Sng-item, multi-lvl

Field Name Input Data
Material 2300-101-XX
Plant 3000
Processing key NETCH
Create pur. req 2
Deliv. Schedule 1
Create MRP list 1
Planning mode 1
Scheduling 1
Planning component select
Display result deselect
Dksplay mat. List select

Select the Enter Icon

RESULTS

The system reports the number of materials planned.

______________________

Click on the Materials button to display the planned orders as a result of running MRP.

Record the materials listed as the result of the MRP run.

Material:____________________

Material:____________________

Material:____________________

Material:____________________


Display the stock requirements list to view the dependent requirements and planned orders for the material specified. Then compare it to the MRP List.

MENU PATH

Logistics>Production>MRP>Evaluations>Stock/reqmts list

Field Name Input Data
Material 2300-101-XX
Plant 3000

Were planned orders generated for this component?

________________


Convert the planned order for the material into a production order.

MENU PATH

Logistics>Production>MRP>Evaluations>Stock/reqmts list

Field Name Input Data
Material 2300-101-XX
Plant 3000

Select the enter icon

To convert the first planned order in the list, place your cursor on the planned order.

MENU PATH

Environment>Convert>Plnd Ord. To prod ord

Field Name Input Data
Total quantity Accept the proposed quantity from the planned order.

Select the Operations button to record the workcenter number.

RESULTS

Workcenter # _______________

Operation description ________________

Select the component button to verify the correct components are listed

Field Name Input Data
Component item 0010 3300-113-yy do not change theses numbers
Component item 0020 3300-120-yy do not change theses numbers
Component item 0030 3300-130-yy do not change theses numbers

Select the Save icon to save the production order

Now that you have converted the planned order to a production order use the follwing menu path to review the current situation.

MENU PATH

List>Refresh

Document the production order number

______________________________


Release the production order to the shop floor. Production orders must be released to the shop floor before any component material is issued or any finished product is received.

MENU PATH

Logistics>Production>Production Control>Order>Release

Field Name Input Data
Order Type PP01
Plant 3000
Order Use the system generated number recorded in the activity above.
Date Selection (Release from and to Delete default dates

Select the Execute icon and verify the status

Field Name Input Data
Status REL PRC MACM SETC

Select the box to the left of the order.

Select the Release button


Issue all component material to the production order and confirm by displaying the stock/requirements list.

MENU PATH

Logistics>Production>Production Control>Environment>Goods movement>Goods issue>Goods issue>Create w. reference> To order

Field Name Input Data
Order Use the system generated production order number generated in the previous activity.
Storage Location 0001
Plant 3000

Select the enter icon

Field Name Input Data
Quantity Enter the quantity you want to issue for the first,second and third components

Select the Copy button

Select the Enter icon

Select the Save icon

Document the system generated goods issue number

RESULTS

_______________________


Confirm completion of all production activity by milestone as proposed for labor and quantity.

MENU PATH

Logistics>Production>Production Control>Confirmation>Enter>For order

Field Name Input Data
Order Use the system generated production order number recorded in the previous activity

Select the Enter icon

Field Name Input Data
Final confirmation Select
Yield to confirm Enter the total quantity on the order as shown in the Total to confirm column (located to the right of this field)

Select the save icon


Receive the finished product into the inventory for the stock location specified

MENU PATH

Logistics>Production>Production Control>Environment>Goods movement>Goods receipt>Goods receipt>Create w. reference>To order

Field Name Input Data
Movement type 101
Storage location 0001
Order Use the system generated production order from activity above.
Plant 3000

Select the Enter icon

Select the Save icon

Document the goods receipt document number

RESULTS

___________________________


Cost Analysis of the Order

MENU PATH

Logistics>Production>Production control>Order>Display

Field Name Input Value
Order Enter the order number from the previous activity

MENU PATH

Goto>Costs>Analysis

Compare the planned v. actual costs for the order.

____________________________________________________________________