- Take the LP model:

Assume that we will apply only one
iteration of the revised simplex. Perform the following:
- Write the LP model in equation form.
- Choose a suitable starting basis.
- Compute the reduced costs corresponding to the chosen basis.
- Determine the nonbasic variable that
will be part of the basis in the following iteration.
- Write the new basis.
- Use the revised simplex method to solve bounded variable LP:

- An LP model with parametric resource availabilities is given by

Obtain the optimal solution
for t ≥ 0.
- Consider the following production planning problem. There are
two production lines in a plant; and both lines produce the same
product. The production capacity of each line is 3,000 units in one
week. Due to high setup costs, the second production line is started
only when the first line has reached its capacity. Define the
decision variables:
x1 : production volume in one week from the first
production line
x2 : production volume in one week from the second
production line Write only the constraints that will enforce the production
restrictions explained above. - Saudi Tables produces
three kinds of tables; school tables, four-leg tables, and
single-drawer tables. Each kind requires wood, paints, and labor
hours for assembly. The requirements for labor hours, wood, and
paints are shown in the table below. The unit revenues are also
shown.
| Kind |
Labor hours |
Wood (kg) |
Paint (kg) |
Unit revenue (riyals) |
| School |
1.5 |
2 |
3 |
260 |
| Four-leg |
3 |
3 |
2 |
280 |
| Single-drawer |
2 |
4 |
2 |
310 |
The available resources are: 900 labor hours; 1,600 kg of wood; and
1,550 kg of paint. Answer the following:
- The goals of the company and their priorities are as follows:
-
Priority 1: obtain revenue of at least 105,000 riyals
- Priority 2:
reduce any additional labor hour
- Priority 3: reduce any additional
paint
- Priority 4: reduce any additional wood
The industrial engineer
needs to plan the production that will meet the goals of the company.
Write the preemptive goal model (do not solve) that will give a suitable
production mix. - Additional resources can be purchased as follows:
- labor hour can be purchased by 6 riyals
- 1 kg of wood can be purchased by 3 riyals
- 1 kg of paint can be purchased by 2 riyals
The goals and their priorities are
- Priority 1: obtain revenue of at least 105,000 riyals
- Priority 2: reduce any additional labor hour cost
- Priority 3: reduce any additional paint cost
- Priority 4: reduce any additional wood cost
Revise the preemptive goal model in (a) to include these costs.
- The industrial engineer in the Arab
Paper Manufacturing Company (WARAQ) is planning the installation
of paper waste gathering system inside the plant. The system
consists of a single line conveyor that will connect the six work
stations inside the plant to a gathering bin. It has been estimated
that the cost of the conveyor gathering system increases linearly
with the length of the conveyor. The figure below shows the layout
of the plant; and the gathering bin is indicated by the label ‘0’.
The distances in meters between the work stations are also shown.

Write the mathematical model that will find the least cost
conveyor system.
- Consider the two-goal model:

If P1 is more important than P2, find the efficient
solution using the goal simplex.