| |
A
network is defined by a set of nodes N and a set of
arcs A. In a compact form, the network is denoted by (N, A).
The nodes are depicted as circles with a number inside, which is used as
a reference to the node and the order does not imply any preference or
order. The arcs are those lines that connect nodes with each
other; and they are drawn with a number on them that indicates a
cost measure.
Networks can simplify many problems we face in
operations research, and luckily, for almost all of them, we have
methods and procedures to solve them. One of these problems is the
minimum spanning tree.
A tree is a network without cycles or loops, and the
spanning tree is a tree that connects all the nodes of the network.
When a tree connects all the nodes with the smallest sum of the arc
costs, the result will be the minimum spanning tree.
We present a labeling technique to find the minimum
spanning tree for a network. I have found that this labeling
technique is easier for students taking an introductory course in
operations research. We will illustrate the technique by means of
a real example on the establishment of an electricity network for the
Kingdom of Saudi Arabia.
Electricity Network for the Kingdom
The Ministry of Water and Electricity has a plan to
connect the major cities of the Kingdom with an interconnect electric
power grid, so there will be central generator units located in
Dhahran.
The generator units will run on natural gas, using the combined cycle
technology. The proposed network will be built out of high voltage
power lines and city-gate transformers. The distances between the
cities in km are shown in the following map.

|
Node |
City |
|
1 |
Dhahran الظهران |
|
2 |
Riyadh الرياض |
|
3 |
Buraidah بريدة |
|
4 |
Hail حائل |
|
5 |
Arar عرعر |
|
6 |
Qrayat القريات |
|
7 |
Tabuk تبوك |
|
8 |
Madina المدينة |
|
9 |
Jeddah جدة |
|
10 |
Abha ابها |
|
11 |
Jazan جازان |
The connections shown in the
map are all possible configuration of the network, when other factors,
such as terrain, are considered. Planners believe the cost of the
construction of the network will be largely dependent on the length of
the network; other components of the network can be treated as fixed
costs, as they are essential parts of the electricity network.
Therefore, the total construction cost can be reduced if the length of
the connections is reduced. In view of this, the problem becomes
of the construction of the minimum spanning tree and the minimum
spanning tree algorithm can be used to find the cheapest configuration
of the electric power network for the Kingdom.
Revised Minimum Spanning Tree Algorithm The basic
minimum spanning tree algorithm works by picking up the nodes of the
network in succession. In any stage of the algorithm, a tree is
constructed that spans a subgroup of the nodes. The algorithm
terminates when all the nodes are connected to the spanning tree.
The steps of the algorithm can summarized as follows:
-
Choose any node in the network.
-
Locate the node closest (cheapest) to the
selected node.
-
Locate the node closest to either one of the
selected nodes, and repeat.
To effectively track the expansion of the tree, we
propose a labeling procedure. The labels establish the connections
of nodes to each other. The labeling procedure defines two kinds
of labels: temporary and permanent. Every node in the network has
a label. The label has two components:
[a,
W]: a is the
cost of connecting the node to the permanently labeled node
W.
The first node has a permanent label [-, -].
The labeling procedure assign temporary labels to all nodes that can be
connected to the permanently labeled nodes. The label of the
temporarily labeled node with the smallest cost component
a is changed to permanent. After this, all
temporary labels are updated and nodes are added, if any. The
steps of the labeling procedure are as follows:
-
Assign permanent label [-, -] to the selected
node.
-
Locate all the nodes that have direct connection
to the permanently labeled nodes, and assign to them temporary
labels.
-
Find the label with the least cost component and
change the status of the label to permanent.
-
If all nodes but one have permanent labels, stop.
Else, go to step 2.
Optimal Configuration of the Electric Power Grid
for the Kingdom We apply the labeling procedure to
the design of the electric power grid for the Kingdom. We can
start from any node; as the solution will not be affected by the start
node. We choose node 1 to be the start node. We can
construct the following table:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
Now, we add the nodes that can be connected to node
1, which is the only permanently labeled node:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Temporary |
Among all temporarily labeled nodes, the node that
has the smallest cost will have a permanent label. Since node 2 is
the only temporality labeled node, its label is changed to permanent:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Permanent |
We add all the nodes that can be connected to the
permanently labeled nodes:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Permanent |
|
3 |
[300, 2] |
Temporary |
|
9 |
[800, 2] |
Temporary |
|
10 |
[1000, 2] |
Temporary |
The temporarily labeled node that has the smallest
cost component is labeled permanent:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Permanent |
|
3 |
[300, 2] |
Permanent |
|
9 |
[800, 2] |
Temporary |
|
10 |
[1000, 2] |
Temporary |
The following table will be:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Permanent |
|
3 |
[300, 2] |
Permanent |
|
9 |
[800, 2] |
Temporary |
|
10 |
[1000, 2] |
Temporary |
|
4 |
[250, 3] |
Temporary |
|
8 |
[400, 3] |
Temporary |
The label of node 4 is changed to permanent.
The resulting table will be:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Permanent |
|
3 |
[300, 2] |
Permanent |
|
9 |
[800, 2] |
Temporary |
|
10 |
[1000, 2] |
Temporary |
|
4 |
[250, 3] |
Permanent |
|
8 |
[400, 3], [450, 4] |
Temporary |
|
5 |
[600, 4] |
Temporary |
|
7 |
[500, 4] |
Temporary |
Node 8 can be connected to two permanently labeled
nodes; 3 and 4. The label with the higher cost should be removed.
The resulting table is:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Permanent |
|
3 |
[300, 2] |
Permanent |
|
9 |
[800, 2] |
Temporary |
|
10 |
[1000, 2] |
Temporary |
|
4 |
[250, 3] |
Permanent |
|
8 |
[400, 3] |
Permanent |
|
5 |
[600, 4] |
Temporary |
|
7 |
[500, 4] |
Temporary |
Proceeding in this manner will produce the following
table:
|
Node |
Label |
Status of label |
|
1 |
[-, -] |
Permanent |
|
2 |
[400, 1] |
Permanent |
|
3 |
[300, 2] |
Permanent |
|
9 |
[300, 8] |
Permanent |
|
10 |
[500, 9] |
Permanent |
|
4 |
[250, 3] |
Permanent |
|
8 |
[400, 3] |
Permanent |
|
5 |
[300, 6] |
Permanent |
|
7 |
[300, 8] |
Permanent |
|
11 |
[160, 10] |
Temporary |
|
6 |
[400, 7] |
Permanent |
This will be the last table since all nodes except
one have permanent labels. From the labels, we can construct the
minimum spanning tree. Node 2 is connect to node 1, node 3 is
connect to node 2, node 9 is connected to node 8, and so forth.
The minimum spanning tree looks like:

The total length of the network can be found by adding the cost part of
the labels, which should be 3,310 km. |
|